Installation carried out entirely by our collaborating company AIR-MONT INSTALACIONES
This installation has consisted of providing a solution to the air conditioning of more than 2,500m2 with an air conditioning system that respects the environment and with energy savings of more than 80% compared to other traditional air conditioning systems.
The equipment used has been 7 units of the model AD-15-VS-100-022 equipped with a centrifugal fan of 13,511 m3/h and 100 Pa of available pressure and 2 units of the model AD-70-VS-100-185 equipped with a centrifugal fan. of 60,644 m3/h and 100 Pa of available pressure.
The total electrical consumption is 52.40 kW with an estimated consumption of 0.020 kW/m2
Air diffusion has been carried out with air ducts with motorized dampers to be able to select the area to be heated and correctly dimensioned air grilles to obtain a correct air flow without disturbing workers or customers.
"We continue working to solve heat problems in industrial and commercial activities"